The technology
The Sliding Form technology is basically applicable for construction of slender reinforced concrete structures. These kind of structures are usually built in three steps sequence:
- reinforcement bars installation
- form assembly
- concrete pour
The Sliding Form technology adapts the industrial chain to the construction process, permitting the three main activities to execute at the same time.
It is based on the manufacture of a small height form (1.00 to 1.35 ms), metallic reinforcing structure and auxiliary structures adapted to a set of synchronous hydraulic jacks moved by an hydraulic system. The resulting form is elevated continuously, allowing the continuous execution of the works mentioned above.
|

|
|
The concrete used for this construction technology must have a setting speed of 4-6 hours to ensure the best result in speed and quality. Usually the concrete layers have 20-30 cm and are executed each 1-2 hour.
Services
ALTAC commercializes the slipform from the company, GBG GLEITBAU Salzburg, company with a great prestige in the international market which has the certification ISO 9001:2000.
ALTAC also has their corresponding certifications ISO 9001:2000 & ISO 14001:1996 for the commercialization of a.m. slipform.
Our intervention can be raised with two possibilities of performance, based on the characteristics of the work:
|
 |
|